    Référence: 20080194
    Date de publication: 30 août 2017

    Promoteur – Intermédiaire Financier

    IS MOLDELECTRICA

    Lieu

    Description

    The project consists of the construction of the power interconnection Isaccea – Vulcanesti – Chisinau between the Republic of Moldova and Romania. It will include the construction of a converter station in Vulcanesti, a 400kV transmission line between Vulcanesti and Chisinau as well as extensions of the existing Vulcanesti and Chisinau substations.

    Objectifs

    Electricity production in Moldova relies on a dominant electricity producer located in the region of Transnistria. The electricity purchased from this power plant and imports from Ukraine meet up to 80% of the overall demand. The project will contribute to the diversification of supply and the energy security of the country. The project will also contribute to connecting the country to the European electricity market, which will increase competition and improve access to cheaper sources of electricity. The project is also expected to foster opportunities for cross-border electricity trade in the South-Eastern Europe region.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Garantie au titre du MPE

    This operation is covered by the EU Guarantee for EIB loans outside the EU.

    Montant BEI envisagé (montant approximatif)

    EUR 80 million

    Coût total (montant approximatif)

    EUR 270 million

    Aspects environnementaux

    An Environmental and Social Impact Assessment (ESIA) is currently under development for the project in the context of the feasibility study, in accordance with Moldovan and EU standards. It will be subject to public consultation. A land acquisition and compensation plan will need to be developed for the high voltage line component once detailed design information is available.

    Passation des marchés

    The Bank will require the promoter to ensure that any procurement procedures are done in accordance with the Bank's Guide to Procurement and the relevant applicable EU public procurement rules.

    Statut

    Signé - 20/12/2017

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).