    Second expansion phase of the Sagunto LNG Plant that will increase the LNG import capacity through the addition of one LNG storage tank and one open-rack seawater vaporiser.

    Objectifs

    The project will increase import capacity of natural gas in line with national energy policy as established by the Spanish Energy Plan for the period 2008-2016 and will contribute to the development of the energy network supplying the European Union. The project is in line with European policy objectives to expand and diversify sources of energy supply.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Approximately 50% of project cost.

    Coût total (montant approximatif)

    Approximately EUR 129 million.

    Aspects environnementaux

    The proposed expansion was already foreseen at the time of the initial construction of the Sagunto LNG terminal and was included in the EIA that received approval from the Ministry of Environment in November 2002. During its actual planning phase it was screened for potential impacts on the environment by the competent authority in 2007, which decided that an additional environmental impact assessment is not required. The decision was made public in the Boletín Oficial del Estado in 2007.

    Passation des marchés

    In 2008 a procurement notice was advertised in the EU Official Journal and the national Boletín Oficial del Estado in order to establish a list of pre-qualified contractors for an EPC contract. The tendering procedure is in progress at present.

    Statut

    Signé - 15/02/2010

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Espagne Énergie