The project concerns BRIANZACQUE SRL's 2025-2029 water and wastewater investment programme, aimed at improving system resilience through interconnections of the water distribution networks, new water sources, and leakage reduction as well as optimisation of existing sewerage treatment facilities.
Objectifs
The aim is to continue support the promoter's investments (e.g. water and wastewater treatment plants, networks and pumping stations) in the Italian region of Lombardy, Province of Monza and Brianza.
Secteur(s)
- Eau, assainissement - Production et distribution d'eau; assainissement, gestion des déchets et dépollution
Montant BEI envisagé (montant approximatif)
EUR 45 million
Coût total (montant approximatif)
EUR 100 million
Aspects environnementaux
The promoter's capacity concerning the environmental and social aspects will be assessed during appraisal. The above-mentioned facilities are likely to fall under Annex II of the environmental impact assessment (EIA) Directive 2011/92/EU (amended by EIA Directive 2014/52/EU), SEA Directive (2001/42/EC), Habitats Directive (92/43/EEC) and Birds Directive (2009/147/EC). The project is expected to bring substantial public health and environmental benefits by improving access to safe and resilient water services, lowering greenhouse gas emissions from reduced water losses and making a more rational use of water resources and protection of local groundwater. Additionally, it will contribute to climate action and environmental sustainability (CA&ES) objectives, in particular to climate adaptation, and sustainable use and protection of water and marine resources.
Passation des marchés
The promoter shall ensure that contracts for the implementation of the Project will be tendered in accordance with the applicable EU procurement legislation Directives 2014/23/EU, 2014/24/EU or 2014/25/EU, where applicable, as well as Directives 92/13/EEC and 89/665/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.
Statut
À l'examen
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).