    Référence: 20240453
    Date de publication: 23 octobre 2024

    Promoteur – Intermédiaire Financier

    VOLTA RIVER AUTHORITY

    Lieu

    Description

    The proposed EUR 45m investment loan from EIB and expected EUR 17m investment grant from EU will finance rehabilitation and upgrade of the 160 MW Kpong hydroelectric dam to better protect against natural disasters, particularly more intense rain in the Volta Lake Basin, from cross-border countries to the North down to the mouth of the river flowing into the Gulf of Guinea. The project includes upgrading slopes of upstream dykes and the 15 spillway gates at the dam generating station.

    Objectifs

    The project, through the rehabilitation and upgrade of essential components protecting the Kpong dam against natural disasters, will ensure the safety and structural integrity of the dam, particularly to withstand heavy rain episodes, which are becoming more frequent in the region, affecting the Volta Lake Basin, from cross-border countries to the North down to the mouth of the river flowing into the Gulf of Guinea.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Under Global Europe NDICI guarantee

    Under EFSD+ Guarantee

    Montant BEI envisagé (montant approximatif)

    EUR 62 million

    Coût total (montant approximatif)

    EUR 62 million

    Aspects environnementaux

    As a rehabilitation on an existing run-of-the-river dam, the project is not expected to result in significant environmental or social impacts, and no resettlement nor additional land use is foreseen. The project was screened in by the national competent authority as subject to a full Environmental and Social Impact Assessment. This assessment is being prepared and a first draft was submitted to the competent authorities and published for public consultation. A Climate Change Risk Assessment for Akosombo and Kpong Hydro Generating Stations and a Flood Risk Assessment and Management Plan are currently being prepared and will be used to apply further adaptation and emergency preparedness measures to the dams. The EIB will verify alignment of the Environmental and Social Impact Assessment and associated documentation with the EIB's Environmental and Social Standards requirements.

    Passation des marchés

    As the promoter operates in the utilities sector as a public undertaking, public procurement procedures as set in the EIB's Guide to Procurement will apply. The promoter has to ensure that the project implementation will be done in accordance with the EIB's Guide to Procurement.

    Statut

    À l'examen - 19/07/2024

    Milestone
    À l'examen

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Ghana Énergie