    Référence: 20230790
    Date de publication: 23 mai 2024

    Promoteur – Intermédiaire Financier

    TERNA - RETE ELETTRICA NAZIONALE SPA

    Lieu

    Description

    The project will support the renewal of the Italian electricity transmission network. The investment programme, to be implemented by 2026, mainly concerns assets reaching the end of their technical life and therefore being at a great risk of failure.

    Objectifs

    The aim is to replace obsolete components (e.g. conductors, transformers, supports, among others) with more modern and efficient ones, to improve the network resilience to adverse climate events and the overall stability and reliability of the national transmission system.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Montant BEI envisagé (montant approximatif)

    EUR 400 million

    Coût total (montant approximatif)

    EUR 812 million

    Aspects environnementaux

    Some of the schemes of the programme may fall under Annex II of the Environmental Impact Assessment (EIA) directive. No EIA is expected according the national legislation as the promoter indicated that no scheme will be above 100 kV with a length of more than 3 Km and renewal of underground cables with a length above 40 km. The environmental and social due diligence will focus on the promoters' capacity to implement the programme in line with EIB's environmental and social standards and requirements.

    Passation des marchés

    The Bank will require the Promoter to ensure that contracts for the implementation of the Project are tendered in accordance with the applicable EU procurement legislation, Directive 2014/25/EU as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

    Statut

    À l'examen - 14/12/2023

    Milestone
    À l'examen

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Italie Énergie