Référence: 20230279
Date de publication: 29 janvier 2025

Promoteur – Intermédiaire Financier

N-ERGIE AG

Lieu

Description

The investment programme concerns the renovation, reinforcement and extension of electricity distribution infrastructure up to 110 kV (overhead lines, underground cables and substations) and the renovation and digitalisation of network control systems. The programme will be implemented in state of Bavaria in southern Germany in the period 2025-2026.

Objectifs

The project caters for demand growth, the connection of network users, the integration of renewables, and the improvement of the quality of service and the efficiency of operations.

Secteur(s)

  • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

Montant BEI envisagé (montant approximatif)

EUR 200 million

Coût total (montant approximatif)

EUR 289 million

Aspects environnementaux

The Project includes components that may fall under Annex II of the Environmental Impact Assessment (EIA) Directive 2011/92/EU as amended by Directive 2014/52/EU, which requires the competent national authority to determine the need for an EIA. All overhead lines and underground cables included in the project have an operating voltages below the threshold for screening set out in the national legislation (110kV) and are hence not subject to an EIA. The impacts that can be typically expected for some schemes relate to visual impact, vegetation clearance, collision and electrocution of flying vertebrates, electromagnetic fields, noise nuisance, and disturbances during construction, as well as the possible impacts on protected fauna and flora (Habitats 92/43/EC and Birds 2009/147/EC).

Passation des marchés

The promoter shall ensure that contracts for implementation of the project have been and will be tendered in accordance with the applicable EU procurement legislation: Directive 2014/23/EU / 2014/24/EU / 2014/25/EU as well as Directive 92/13/EEC or Directive 89/665/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

Statut

À l'examen - 11/06/2024

Milestone
À l'examen

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Allemagne Énergie