    Référence: 20220338
    Date de publication: 17 août 2023

    Promoteur – Intermédiaire Financier

    E.ON DEL-DUNANTULI ARAMHALOZATI ZRT,ELMU HALOZATI ELOSZTO KFT,MAVIR MAGYAR VILLAMOSENERGIA-IPARI ATVITELI RENDSZERIRANYITO ZRT,MINISTRY OF ENERGY - HUNGARY

    Lieu

    Description

    The project will strengthen and expand the transmission and distribution networks of the three project promoters.

    Objectifs

    Among other, the project will cater additional power requirements of two battery manufacturing facilities, located in the less developed regions of Hungary. In detail, one is located at an existing industrial site (Göd) and another at a greenfield industrial site (Iváncsa).

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Montant BEI envisagé (montant approximatif)

    EUR 90 million

    Coût total (montant approximatif)

    EUR 123 million

    Aspects environnementaux

    The project comprises several electricity transmission and distribution schemes, with voltage levels ranging from 132 kV to 400 kV. None of the project schemes falls under Annex I of the Environmental Impact Assessment (EIA) Directive 2011/92/EU (amended by EIA 2014/52/EU). Some of the schemes may fall under Annex II of EIA Directive 2011/92/EU (amended by 2014/52/EU), which requires the competent national authority to determine the need for an EIA. The environmental and social due diligence will include a review of relevant screening decisions and/or EIAs, and focus on the three promoters' capacity to implement the project in line with the EIB's socio-environmental standards and requirements.

    Passation des marchés

    The promoters have to ensure that contracts for the project implementation have been and shall be tendered in accordance with the applicable EU procurement legislation, Directives 2014/25/EU and 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.

    Statut

    Approuvé - 12/09/2023

    Milestone
    À l'examen
    Approuvé
    12 septembre 2023

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).