Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
Référence: 20220338
Date de publication: 17 août 2023

Promoteur – Intermédiaire Financier

E.ON DEL-DUNANTULI ARAMHALOZATI ZRT,ELMU HALOZATI ELOSZTO KFT,MAVIR MAGYAR VILLAMOSENERGIA-IPARI ATVITELI RENDSZERIRANYITO ZRT,MINISTRY OF ENERGY - HUNGARY

Lieu

Description

The project will strengthen and expand the transmission and distribution networks of the three project promoters.

Objectifs

Among other, the project will cater additional power requirements of two battery manufacturing facilities, located in the less developed regions of Hungary. In detail, one is located at an existing industrial site (Göd) and another at a greenfield industrial site (Iváncsa).

Secteur(s)

  • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

Montant BEI envisagé (montant approximatif)

EUR 90 million

Coût total (montant approximatif)

EUR 123 million

Aspects environnementaux

The project comprises several electricity transmission and distribution schemes, with voltage levels ranging from 132 kV to 400 kV. None of the project schemes falls under Annex I of the Environmental Impact Assessment (EIA) Directive 2011/92/EU (amended by EIA 2014/52/EU). Some of the schemes may fall under Annex II of EIA Directive 2011/92/EU (amended by 2014/52/EU), which requires the competent national authority to determine the need for an EIA. The environmental and social due diligence will include a review of relevant screening decisions and/or EIAs, and focus on the three promoters' capacity to implement the project in line with the EIB's socio-environmental standards and requirements.

Passation des marchés

The promoters have to ensure that contracts for the project implementation have been and shall be tendered in accordance with the applicable EU procurement legislation, Directives 2014/25/EU and 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.

Statut

Approuvé - 12/09/2023

Milestone
À l'examen
Approuvé
12 septembre 2023

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Hongrie Énergie