Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
    Référence: 20210011
    Date de publication: 25 octobre 2021

    Promoteur – Intermédiaire Financier

    ENERGA SA

    Lieu

    Description

    The programme concerns investment schemes in the electricity distribution network of northern and central Poland over the period 2021-2023. The programme includes the construction of new distribution assets, modernisation of the existing network, and installation of smart meters and other smart grid components.

    Additionality and Impact

    The program comprises the reinforcement and modernisation of the electricity distribution network in Poland, consistently with the country's National Energy and Climate Plan and in alignment with EIB public policy goals.


    The programme schemes are located in eight regions in the country, all comprising Cohesion Priority Regions. The programme helps addressing market failures linked to negative climate and environmental externalities (by enabling the future integration of renewable generation, while also contributing to the electrification of the economy) as well as improving security of supply, a public good. The project's results and quality are deemed good in terms of economic welfare by virtue of the benefits it generates, as well as from a governance perspective. It is also deemed to created additional employment.


    With this loan, the Counterpart receives significant added value from the Bank, in the context of the scarcity of attractively priced, PLN-denominated funding with similar long maturities available on the Polish market.

    Objectifs

    The programme will allow the Promoter to connect new users, including renewable generation, as well as to maintain or improve the reliability and quality standards of electricity supply.

    Commentaires

    N/A

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Montant BEI envisagé (montant approximatif)

    EUR 150 million

    Coût total (montant approximatif)

    EUR 906 million

    Aspects environnementaux

    Some programme schemes may fall under Annex II of Directive 2014/52/EU, amending the EIA Directive 2011/92/EU thus requiring a review by the competent authorities at the planning/consent stage with due regard to the necessity for environmental and biodiversity impact and appropriate assessments.

    Passation des marchés

    The Bank will require the Promoter to ensure that contracts for implementation of the project have been and shall be tendered in accordance with the applicable EU procurement legislation, Directive 2014/25/EU as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.

    Statut

    Signé - 16/12/2021

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Pologne Énergie