Référence: 20190755
Date de publication: 28 juillet 2020

Promoteur – Intermédiaire Financier

RETE FERROVIARIA ITALIANA SPA

Lieu

Description

The project consists of the upgrading of the existing Napoli-Bari railway line to higher technical standards, including increase of maximum design speed to 200 km/h and doubling of existing single track sections. The Napoli-Bari railway is a mixed traffic line (passenger and freight) that is part of the Scandinavian-Mediterranean Trans-European Transport Network (TEN-T) corridor. The project connects the biggest city in Southern Italy, Napoli, with another major city, Bari, crossing two southern Italian Regions (i.e. Campania and Puglia).

Objectifs

The project is expected to increase the quality of rail services in two less-developed Regions in Southern Italy (i.e. Campania and Puglia). The project is also expected to significantly reduce travel times, promoting modal shift from road and air to rail, generate vehicle operating cost savings as well as environmental and safety benefits. Hence, the project will contribute to promoting travel by rail, enhance sustainable transport, reduce greenhouse gas (GHG) emissions and therefore mitigate climate change in line with EU objectives.

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 2000 million

Coût total (montant approximatif)

EUR 6322 million

Aspects environnementaux

The project is part of the National Transport Plan (Allegato Infrastrutture – Connettere l'Italia) for which a Strategic Environmental Impact study was undertaken according to SEA Directive 2001/42/EC. The investment proposed under the project falls under Annex I of the Environmental Impact Assessment Directive 2011/92/EU (as amended by Directive 2014/52/EU). The environmental impacts of the project, the environmental impact assessment (EIA) procedure and the need for assessment according to the Habitats Directive 92/43/EEC will be analysed during the appraisal. The project will significantly improve the rail connection between Napoli and Bari and is expected to result in modal shift from road and air to rail with the corresponding environmental benefits in terms of reduction of noise, GHG emissions and pollution.

Passation des marchés

The Bank will require the Promoter to ensure that contracts for the implementation of the project have been and will be tendered in accordance with the relevant applicable EU procurement legislation, 2014/25/EU, where applicable, as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.

Statut

Signé - 28/10/2020

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Italie Transports