    Référence: 20170728
    Date de publication: 5 février 2018

    Promoteur – Intermédiaire Financier

    INDORAMA ELEME FERTILIZER & CHEMICALS LTD

    Lieu

    Description

    Construction of a second ammonia and urea fertilizer plant next to the existing facilities of the promoter in Port Harcourt, Nigeria. The project will install the same capacity (2 300 mtpd ammonia and 4 000 mtpd urea) and use the same technology, contractors, engineering and equipment as the first fertilizer plant, thereby minimising project execution risks. It will also benefit from existing infrastructure and a long-term supply contract. The project will build on growing demand and the success of the first fertilizer plant.

    Objectifs

    The project aims both to provide access to competitive urea supply for the farmers in the wider region and to export urea. The project will have a number of development benefits including increased food security by giving farmers access to competitive supply of urea.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    USD 125 million (EUR 101 million)

    Coût total (montant approximatif)

    USD 1100 million (EUR 893 million)

    Aspects environnementaux

    Fertilizer projects of the kind proposed fall under Annex I of the EIA Directive 2014/52/EU amending Directive 2011/92/EU, requiring an Environment Impact Assessment (EIA). Taking into account applicable national and international guidelines, the promoter has prepared an EIA and an Environmental and Social Management plan and submitted them to the Federal Ministry of Environment in Nigeria. The environmental and social details and issues will be established during the project appraisal, including conformity check with EU directives and industrial emissions requirements.

    Passation des marchés

    The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement.

    Statut

    Signé - 12/06/2018

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Nigéria Industrie