    Référence: 20170313
    Date de publication: 12 septembre 2017

    Promoteur – Intermédiaire Financier

    REPUBLIC OF SLOVENIA

    Lieu

    Description

    The Slovenian Celje-Pragersko railway line is located on the Baltic-Adriatic and Mediterranean Core Network Corridors. The line currently represents a bottleneck in passenger and freight transport due to insufficient load capacity and limited interoperability. The project concerns construction works in the Poljcane station, the Poljcane–Slovenska Bistrica section and the Slovenska Bistrica station. The works cover reconstruction of substructure and superstructure, construction of platforms, grade-separated crossings, underpasses, as well as adjustments of energy, signalling-safety and telecommunication devices.

    Objectifs

    The project will upgrade the Poljcane-Slovenska Bistrica double-track section with the main objective of increasing the load capacity and improving the interoperability of the railway line.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 18 million

    Coût total (montant approximatif)

    EUR 58 million

    Aspects environnementaux

    The pertinence to Annexes I and II of the Environmental Impact Assessment (EIA) Directive, the screening decisions, the EIA and the development consents will be reviewed during appraisal. The project's potential impact on protected areas and species, in accordance with the Habitats Directive (92/43/EEC) and Birds Directive (2009/147/EC) will also be appraised. A modal shift thanks to increased rail-based mobility can be expected (due to increased speed and capacity), thus also decreasing traffic-related greenhouse gas emissions, although to a limited extent. Details will be checked during appraisal.

    Passation des marchés

    The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2004/17/EC, or 2014/25/EU where applicable, as well as Directives 89/665/EEC and 92/13/EEC), as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.

    Statut

    Approuvé - 27/10/2017

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Slovénie Transports