Référence: 20170288
Date de publication: 10 octobre 2018

Promoteur – Intermédiaire Financier

MINISTRY OF REGIONAL DEVELOPMENT AND INFRASTRUCTURE

Lieu

Description

The project consists of the construction and upgrading of the existing E-60 road between Chumateleti and Khevi to 2 x 2 dual carriageway standard. The works on the left branch of the Chumateleti-Khevi section of the highway starts approximately 1.3km before the eastern portal of the existing Rikoti tunnel and ends near the village of Khevi. The total length of the left branch of the road is approximately 11.6km long. The works on the right branch start at the north-western portal of the existing Rikoti Tunnel and run for approximately 8.6km to Khevi.

Objectifs

The proposed project will support the Georgian Government in implementing its 2017-2020 upgrade/construction programme of priority roads throughout the country. The objective is to promote sustainable road infrastructure development providing efficient transportation, enhancing cross border/regional connectivity and ensuring short and long-term benefits for all users.

Secteur(s)

Garantie au titre du MPE

This operation is covered by the ELM Guarantee.

Montant BEI envisagé (montant approximatif)

EUR 67 million

Coût total (montant approximatif)

EUR 136 million

Aspects environnementaux

If located in the EU, the project would be subject to the Environmental Impact Assessment (EIA) Directive (2014/52/EU amending EIA Directive 2011/92/EU) and the Birds and Habitats Directives (2009/147/EC and 92/43/EEC respectively). There are no natural 2000 habitats. No protected areas will be impacted. According to the Environmental and Social Impact Assessment (ESIA) submitted by the Promoter, construction and operation of the East West Highway within Chumateleti-Khevi section will not have impact on the protected areas, as the closest national park of Borjomi-Kharagauli is approximately 6kms from the road corridor.

Passation des marchés

The EIB will require the Promoter to ensure that any procurement procedures on the project are done in accordance with the EIB Guide to Procurement, the relevant applicable EU public procurement rules and relevant applicable local legislation. In particular clause 3.4.5 of EIB Guide to Procurement will be applicable as this project is co-financed with World Bank. Publication of tender notices will take place in the Official Journal of the European Union (OJEU), as required.

Statut

Approuvé - 19/11/2018

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).