    Référence: 20170205
    Date de publication: 3 décembre 2018

    Promoteur – Intermédiaire Financier

    JP SRBIJAGAS NOVI SAD

    Lieu

    Description

    The project consists of the construction of the Serbian section of a gas interconnector between Serbia and Bulgaria to allow for the transfer of between 1 and 1.8 billion cubic metres of natural gas annually from Bulgaria to Serbia and 0.15 billion cubic meters from Serbia to Bulgaria. The project will contribute to diversification of supply routes and potential supply sources of natural gas to South-East European region.

    Objectifs

    The project aims to provide diversification of gas supply routes and sources to the Serbian and South East Europe gas market and to improve market integration and security of supply to both Serbia and Bulgaria.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Garantie au titre du MPE

    This operation is covered by the ELM Guarantee.

    Montant BEI envisagé (montant approximatif)

    EUR 25 million

    Coût total (montant approximatif)

    EUR 86 million

    Aspects environnementaux

    The Bulgaria-Serbia gas interconnector project is part of the "Energy Sector Development Strategy of the Republic of Serbia", which went through a Strategic Environmental Assessment process. At the feasibility stage an international consultant performed an Environmental and Social Impact Assessment (ESIA) of the project. The environmental permitting process is still ongoing with plans to be completed by the end of 2018. The pipeline route is proposed outside populated areas and in a way to avoid environmentally sensitive areas to the extent possible. It passes through largely agricultural land and forested areas. Impacts that can be typically expected are mainly temporary and relate to construction works. These impacts can usually be well managed by appropriate measures taken by the construction company in order to avoid unacceptable nuisance to other parties and the public. An assessment of the environmental procedures and capabilities of the Promoter, the potential environmental and social impacts of the Project along with checking alignment with the relevant EU Directives will be carried out during the appraisal.

    Passation des marchés

    The Bank will require the promoter to ensure that any procurement procedures are done in accordance with the Bank's Guide to Procurement and the relevant applicable EU public procurement rules.

    Statut

    Signé - 20/05/2021

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Serbie Énergie