Date de publication: 22 mai 2015
Promoteur – Intermédiaire Financier
KELAG-KAERNTNER ELEKTRIZITAETS-AGLieu
Description
Investment programme in heating, wind/hydro power production and grid investments during 2014-2017 by the regional multi-sector energy company of Carinthia.
Objectifs
The project will promote the development and modernisation of the electricity distribution and district heating networks of KELAG, as well as adding and restoring renewable energy production. It will enable KELAG to maintain/improve the current levels of network reliability and safety and add new customer connections.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 100 million
Coût total (montant approximatif)
EUR 212 million
Aspects environnementaux
Hydro, wind and district heating schemes are expected to fall under Annex II of Directive 2011/92/EU on environmental impact assessment (EIA), whereby the need for an EIA is determined by the competent national authority. Electricity distribution at medium and low voltage, district heating and refurbishments of hydropower plants are typically implemented with low or insignificant environmental impact.
Passation des marchés
The Bank will require the promoter to ensure that contracts for the implementation are tendered in accordance with the relevant applicable EU procurement legislation (Directives 2004/17/EC and 2007/66/EC (amending Directives 1989/665/EEC and 1992/13/EEC)), with publication of tender notices in the EU Official Journal, as and where required.
Statut
Signé - 3/07/2015
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).