Modernisation and extension of electricity distribution network in Slovakia for 2014-2018
Objectifs
Competitive and Secure Energy (incl. TEN-E) 100% Economic and Social Cohesion (transversal) 100%
Commentaires
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 125 million
Coût total (montant approximatif)
EUR 253 million
Aspects environnementaux
The project includes facilities that fall under Annex II of the EIA Directive (2011/92/EU). The impacts that can be typically expected for some schemes relate to visual impact, vegetation clearance, an impact on flying vertebrates, electromagnetic fields, noise nuisance, and disturbance during construction. Medium Voltage (MV) and Low Voltage (LV) schemes are expected to have minimal or null environmental impacts.
Passation des marchés
The promoter is a contracting entity that falls under the Utilities Directive 2004/17/EC, and is therefore required to tender works, supplies and services contracts following public procurement rules, including the publication in the Official Journal of the EU (OJEU) where appropriate.
Statut
Signé - 23/12/2014
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).