Date de publication: 25 juillet 2013
Promoteur – Intermédiaire Financier
OPERATOR GAZOCIAGOW PRZESYLOWYCH GAZ - SYSTEM SALieu
Description
Construction of the LWOWEK-ODOLANOW gas pipeline in Poland, contributing to increased system capacity, energy security and diversification of natural gas supplies.
Objectifs
The project would add capacity and robustness to the existing Polish gas transmission system and allow better connectivity to new gas supplies, including the Swinoujscie LNG terminal. Increasing penetration of gas will displace less efficient and more polluting sources of energy, thereby contributing to EU objectives of rational use of energy and environmental protection. The project is therefore eligible under Article 309 point (a) projects for developing less-developed regions and/or point (c) common interest.
Commentaires
Secteur(s)
- Énergie - Transports et entreposage
Montant BEI envisagé (montant approximatif)
PLN 410 million (EUR 98 million)
Coût total (montant approximatif)
PLN 1008 million (EUR 241 million)
Aspects environnementaux
Current information suggests that the project components will fall under Annex I of the Environmental Impact Assessment Directive (2011/92/EU), requiring the Promoter to undertake an EIA.
Passation des marchés
The investments under the project are subject to the national and EU procurement provisions defined for entities operating in the water, energy, transport and postal services sectors.
Statut
Signé - 16/06/2014
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.