Référence: 20110563
Date de publication: 25 janvier 2012

Promoteur – Intermédiaire Financier

Ministry of Transport and State Revenue Committee

Lieu

Description

The proposed operation involves the reconstruction and modernisation of the border crossing points (BCPs) in Bagratashen, Bavra and Gogavan along the border with Georgia, along with seven kilometres of associated access roads including one major new bridge, as well as internal roads at the border crossings.

Objectifs

The project will facilitate free movement of persons and goods across borders, while at the same time maintaining secure borders by provision of all necessary conditions for effective performance of border, customs and other controls. It will significantly contribute towards the enhancement of inter-agency cooperation efficiency, including technical capacity for information exchange between executive authorities on border management related issues and on border control operational procedures.

Commentaires

This operation is covered by the EU Guarantee for EIB loans outside the EU.

Secteur(s)

Garantie au titre du MPE

This operation is covered by the ELM Guarantee.

Montant BEI envisagé (montant approximatif)

EUR 43 million

Coût total (montant approximatif)

EUR 62 million

Aspects environnementaux

If the project was located in the EU, it would fall under Annex II of the EIA Directive 85/337/EEC, as amended by Directives 97/11/EC and 2003/35/EC. The project was screened in by the Competent Authority given its trans-boundary status, the new bridge construction and the total site area being greater than 1500 sq.m. During appraisal the Bank shall review the EIA process adopted to date to confirm that it complies with applicable domestic legislation, the principles laid out in the EU Directives and any other relevant international conventions to which the Republic of Armenia is party.

Passation des marchés

The Bank will require the promoter to ensure that implementation of the project will be done in compliance with the Bank's Guide to Procurement. The contracts for design, works and supply of equipment will be procured by UNDP, being the project manager, in accordance with procurement policies and rules acceptable to the Bank and in compliance with international standards. The calls for tenders and the award notices will be published in the OJEU as appropriate.

Statut

Signé - 7/08/2012

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Arménie Transports