Date de publication: 7 décembre 2011
Promoteur – Intermédiaire Financier
Autorità Portuale di Genova
Lieu
Description
The project consists of the construction of a new container terminal and the improvement and extension of internal road and rail connections, in the port of Genoa.
Objectifs
The project will provide the capacity needed to meet the needs of expected container traffic growth.
Secteur(s)
Montant BEI envisagé (montant approximatif)
Up to EUR 125 million
Coût total (montant approximatif)
Up to EUR 250 million
Aspects environnementaux
Compliance of the various project components with the EU EIA Directive 85/337/EEC, amended by Directives 97/11/EC and 2003/35/EC, and biodiversity assessment requirements will be verified during appraisal, and the status of any environmental studies and public consultations will be reviewed.
Passation des marchés
Autorità Portuale di Genova is a contracting authority within the meaning of Directive 2004/17/EC of 31 March 2004. The Bank will require the Promoter to ensure that contracts for the implementation of the project have been / will be tendered in accordance with the above procurement legislation, with parallel publication of tender notices in the OJEU, as and where appropriate. The status of procurement for the various project components and the procedures for the selection of the future port terminal concessionaire will be checked during appraisal.
Statut
Signé - 31/07/2012
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).