    Référence: 20100482
    Date de publication: 28 décembre 2010

    Promoteur – Intermédiaire Financier

    The project promoter is a renewable energy subsidiary of a large Austrian integrated energy utility group that is controlled by the region of Burgenland.

    Lieu

    Description

    The project consists of the construction and operation of six onshore wind parks located in the Austrian Burgenland region.

    Objectifs

    The development of wind power contributes to EU and national renewable energy objectives, as well as Austrian’s economic development.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Up to EUR 200 million

    Coût total (montant approximatif)

    Up to EUR 335 million

    Aspects environnementaux

    All wind farms proposed fall under Annex II of the EIA Directive 85/337/EC. Therefore they can be subject to an EIA on a case by case basis decision or defined criteria set by the competent authority. One wind farm has been screened in during this process, and has undergone an EIA process. The exact EIA status of the remaining schemes will be clarified along with the environmental assessment of all wind farms (including impacts on nature conservation zones and potential cumulative impacts with other wind projects).

    Passation des marchés

    The promoter is a public undertaking but it is not subject to public procurement procedures in the sense of the EU Procurement Directive 2004/17/EC as the Commission has exempted those public contracts from the procurement directive which are awarded to enable to carry out electricity generation in Austria (decision 2008/585EC of 7th July 2008). The Bank will however ensure that procurement procedures applied ensure an appropriate selection of works, goods and services offered at competitive prices.

    Statut

    Signé - 31/10/2011

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Autriche Énergie