Référence: 20090448
Date de publication: 3 mars 2010

Promoteur – Intermédiaire Financier

SPA AUTOVIE VENETE

Lieu

Description

Widening of the A4 18,5 km highway section between Quarto d'Altino and San Donà di Piave (Veneto) and the 41 km highway section between Palmanova (A23 junction - Friuli Venezia Giulia) to Portogruaro (A28 junction - Veneto)

Objectifs

The expected economic benefits include time savings and vehicle operating cost reductions for road users due to enhanced road capacity. The project offers safety as well as environmental benefits, as congestion will be reduced and standards improved.

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 375 million

Coût total (montant approximatif)

EUR 1180 million

Aspects environnementaux

Please refer to the Environmental and Social Data Sheet for details. Prior to the disbursement relevant for each section the promoter will provide the Bank with written confirmation from the competent authority that the provisions of the Habitats Directive have been complied with.

Passation des marchés

The promoter is a majority publicly owned company, subject to the provisions of Directive 2004/18/EC, as transposed into national law. All contracts are being procured accordingly.

Statut

Signé - 27/02/2017

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Italie Transports