    Référence: 20050109
    Date de publication: 21 octobre 2005

    Promoteur – Intermédiaire Financier

    Eurosviluppo Elettrica S.p.A., a special purpose project vehicle owned jointly by a Spanish electricity company and an Italian multi-utility company

    Lieu

    Description

    The project involves the design, construction, commissioning and operation of a large scale natural gas-fired co-generation plant comprising two identical CCGT units with a combined capacity of 800 MWe.

    Objectifs

    The proposed project will install advanced power generation technology with a relatively low environmental impact; contribute to market liberalisation and facilitate decommissioning of old, inefficient and polluting oil-fired power stations elsewhere in Italy and/or reduce imports. Due to cogeneration the plant will have a high energy-conversion efficiency, which will contribute to the rational use of energy.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Up to EUR 200 million.

    Coût total (montant approximatif)

    The project cost is expected to be in the region of EUR 400 million.

    Aspects environnementaux

    The project falls under Annex I of the EIA-Directive 97/11/EC requiring a full EIA. The permit was granted by the competent authority and has set out atmospheric emission limits which are in line with EU’s Large Combustion Plant Directive; indicating a relatively low level of pollution due to this modern type of CCGT and the use of natural gas. Concerning the “Habitats”-Directive 92/43/EEC and the Natura 2000 network, the permit indicates one Site of Community Importance (SIC, named “Foce del Neto”), situated at a distance of 13 km to the project’s location, for which the competent authority concluded in its permit that the investment is not expected to have a significant impact on the site.

    Passation des marchés

    The plant will be built under a turn-key contract, for which the promoter has launched an international enquiry procedure on a competitive, restricted basis and sent out call for bids by the end of 2004 inviting several internationally known gas-turbine manufacturers to bid for the implementation of the project.

    Statut

    Signé - 6/12/2006

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Italie Énergie