Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
    Référence: 20040281
    Date de publication: 17 août 2004

    Promoteur – Intermédiaire Financier

    Hitaveita Sudurnesja HF
    Brekkustig 36
    260 Reykjanesbaer
    Iceland

    Mr Júlíus Jónsson, CEO

    Landsvirkjun
    Haaleinsbraut 68
    103 Reykjavik
    Iceland

    Mr Stefan Pétursson, CFO

    Lieu

    Description

    Development of an existing geothermal field (Reykjanes) and construction of a new geothermal power plant with a capacity of 100 MWe. The project is located 25km south-west of Reykjavik. The promoter is the power, water and district heat utility serving the regions of Sudurne, Hafnarfjordur and Vestmanneyjar in the south-west of Iceland. It is intended to provide additional supplies of electricity to meet the projected growth in electricity demand in the region, mainly from an expanding aluminium plant, and for export to the national power grid.

    Objectifs

    The project concerns the development of indigenous geothermal energy resources to generate electricity and heat, thereby minimising the use of fossil fuels and emissions of air pollutants. The project aims at the cost-effective supply of power and heat to meet growing demand.

    Commentaires

    Development of indigenous resources, regional and global environment including climate change.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Up to EUR 75 million.

    Coût total (montant approximatif)

    The investment is estimated to be around EUR 110m for the plant and EUR 50m for related grid investment.

    Aspects environnementaux

    The project was subject to an Environmental Impact Assessment (EIA) in accordance with national legislation, which is based on the EU Directives 85/337 and 97/11 (the project falls under Annex II of Directive 97/11). The promoter prepared environmental impact statements (EIS), which were approved by the Planning Agency, after seeking public consultation and the opinions of the relevant competent authorities. Part of the geological formations concerned by the project are subject to special protection under national nature conservation legislation, however the EIA concluded that the project would not cause significant adverse impact.

    Passation des marchés

    The project will be implemented under a number of separate works, supply and services contracts, which will be procured in line with the requirements of the relevant EU Directive (93/38/EEC), including publication in the Supplement to the EU Official Journal. Details will be verified during appraisal. Tenders for the turbine/generator sets were submitted in February 2004.

    Statut

    Signé - 12/11/2004

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Islande Énergie