Date de publication: 16 juin 2004
Promoteur – Intermédiaire Financier
Office National de l’Électricité.Lieu
Description
The project concerns investment in the Mohammédia power plant located on the coast 25 km north of Casablanca, which was built in the early 1980s by Ansaldo on the basis of an EDF design. The plant has an installed capacity of 600 MW (15% of the country’s electricity) generated by four 150 MW steam turbines (two coal-fired and two heavy-fuel-oil-fired).
Objectifs
The new schemes aim to reduce the plant’s environmental impact and improve its performance. They will serve to eliminate operational inefficiencies through modification of the boiler design and improvement of coal pulverisation capacity.
Commentaires
Electricity.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 40 million loan from EIB own resources with interest subsidy from the MEDA II budget.
Coût total (montant approximatif)
Around EUR 100 million.
Aspects environnementaux
The investments concerning the coal-fired turbines include the requisite equipment to reduce air pollution, recover and process fly and heavy ash, reduce the consumption of regeneration products and separate and treat wastewater.
Passation des marchés
The different components of the project have been put out to tender in separate lots in accordance with the Bank’s rules.
Statut
Signé - 4/11/2004
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).