Référence:
20010413
Date de publication: 17 février 2005
Date de publication: 17 février 2005
Promoteur – Intermédiaire Financier
Compania Nationala de Cai Ferate – CFR - SALieu
Description
The project includes the rehabilitation and modernization of the 184 km railway line from Curtici to Simeria, along Pan-European Transport Corridor IV, to reach maximum speeds of 160 km/h.
Objectifs
- sustainable mobility along the Corridor IV,
- increased travel speeds,
- reduced travel time for passengers and goods,
- increased transport safety,
- increased inter-operability with EU standards.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 300 million.
Coût total (montant approximatif)
EUR 850 million.
Aspects environnementaux
The majority of the works will be on the existing railway right-of way and will not require particular environmental studies. However, the station refurbishments and the section of re-alignment will be subject to national and EU environmental regulations and requirements.
Passation des marchés
Procurement will be undertaken in line with the EIB Guide to Procurement.
Statut
Signé - 27/12/2005