The main objectives of this Works contract are:
(a) Refurbish the raw water intakes
(b) Construct a 5,000 m3/day treatment plant to improve water quality and increase the quantity to distribute to the consumers.
The construction works will include Preparatory Works, Works at ARA-Centro Intake, Works at FIPAG Intake, Civil, Structural and Building Works at the Treatment Plant Site and Mechanical and Electrical Works at the Treatment Plant Site.
- Date: 10/12/2025
- Reference: 20190331-10
Corrigendum
- Download the notice of 02/02/2026
Corrigendum
- Download the notice of 13/01/2026
Contract notice
- Download the notice of 10/12/2025
- Deadline for receipt of tenders or requests to participate: 23/01/2026
Disclaimer
This procurement is conducted by the EIB Borrowers/Promoters in accordance with the Guide to Procurement for the contract under the EIB-financed project. The EIB is not a party to the contract and its role is limited to those defined in the Guide to Procurement.