Date de publication: 3 mai 2024
Promoteur – Intermédiaire Financier
WEB WINDENERGIE AGLieu
Description
The project concerns the implementation and operation of a 62,8 MW wind farm in Spannberg / Lower Austria.
Objectifs
The main goal is to reduce carbon and air pollution emissions, which are externalities that the market fails to address. The wind farm will also foster the integration of new, variable renewable generation technologies in the market. Therefore, the EIB's loan will fill the unmet demand of projects developing new renewable capacity, including those with market-exposed structures and instruments.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 74 million
Coût total (montant approximatif)
EUR 114 million
Aspects environnementaux
Wind farms fall under Annex II of the Environmental impact assessment (EIA) Directive 2014/52/EU (amending 2011/92/EU), requiring the competent authorities to determine whether an EIA is required. The project was subject to an EIA. During appraisal, the project's authorization procedures will be further assessed. This includes a verification of compliance of authorisation processes with relevant EU Directives.
Passation des marchés
The European Commission has exempted all contracts which are being awarded to implement electricity generation projects in Austria from the scope of the Utilities Directive. No public procurement is required.
Statut
Signé - 31/07/2024