Search En menu en ClientConnect
Search
Results
Top 5 search results See all results Advanced search
Top searches
Most visited pages
    Reference: SG/E/2018/10
    Received Date: 05 February 2018
    Subject: Trans Adriatic Pipeline
    Complainant: Confidential
    Allegations: Alleged negative environmental, social and economic impacts of the project, in addition to infringements linked to the implementation of the project
    Type: E - Environmental and social impacts of financed projects
    Suggestions for improvement: no
    Admissibility*
    Assessment*
    Investigation*
    Dispute Resolution*
    Consultation*
    Closed*
    8/02/2018
    27/12/2018
    10/03/2020

    * Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.

    Case Description

    Complaint  

    On 5 February 2018, the EIB Complaints Mechanism (EIB-CM) received a complaint alleging negative environmental, social and economic impacts of the project, in addition to infringements linked to the implementation of the project

     

    Project Information