Reference: SG/E/2016/03
Received Date: 06 April 2016
Subject: Nam Theun 2 Hydroelectric
Complainant: CEE Bankwatch Network
Allegations: Alleged non-compliance with the Bank's environmental and social standards and human rights
Type: E - Environmental and social impacts of financed projects
Suggestions for improvement: no
Admissibility*
Assessment*
Investigation*
Dispute Resolution*
Consultation*
Closed*
6/04/2016
18/08/2017
4/07/2018
6/11/2018

* Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.

Case Description

Complaint

On 6 April 2016, the EIB Complaints Mechanism (EIB-CM) received a complaint in relation to the Nam Theun 2 Hydroelectric project concerning (i) the EIB’s reporting on the project to the European Commission, the European Parliament, the Council and the public; (ii) the EIB’s compliance with applicable transparency requirements; and (iii) the EIB’s monitoring of the project’s compliance with the Bank’s environmental and social standards and with the provisions of the Finance Contract.

Project Information