    Reference: SG/E/2022/10
    Received Date: 19 April 2022
    Subject: Programme National Assainissement PNA II
    Complainant: Confidential
    Allegations: Alleged risk that the project caused groundwater and surface water pollution, hygiene and public health issues.
    Type: E - Environmental and social impacts of financed projects
    Admissibility*
    Assessment*
    Investigation*
    Dispute Resolution*
    Consultation*
    Closed*
    19/05/2022
    16/06/2022

    * Admissibility date reflects the date the case was officially registered. All other dates pertain to the date in which a stage was completed.