    Referenz: 20180740
    Veröffentlichungsdatum: 6 April 2020

    Projektträger – zwischengeschaltetes Finanzinstitut

    UAB IGNITIS GRUPE

    Ort

    Beschreibung

    The project will finance a 94 MW onshore wind farm located in the northern part of Poland in Pomeranian Voivodship, approximately 50 km from the coastline of the Bay of Gdansk.

    Ziele

    The project will contribute to environmental and security of energy supply objectives. The project is located in a Cohesion priority region. It is therefore eligible under Article 309 (a) projects for developing less-developed regions and (c) common interest. The financing of this project would contribute to the EIB's lending priority policy on social cohesion, renewable energy and climate action.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    PLN 258 million (EUR 60 million)

    Gesamtkosten (voraussichtlicher Betrag)

    PLN 581 million (EUR 134 million)

    Umweltaspekte

    Windfarms falls under Annex II of Directive 2011/92/EU (as amended by Directive 2014/52/EU) according to which the Member States shall determine whether the project shall be made subject to an assessment based on defined criteria. According to national legislation, windfarms exceeding certain criteria are subject to a mandatory Environmental Impact Assessment (EIA). This was the case for the project. The environmental studies for the EIA process were undertaken and the competent authorities have granted approval containing requirements to mitigate environmental impacts accordingly. Residual impacts were classified of small magnitude and low significance.

    Auftragsvergabe

    The project will be operating without exclusive or special rights within the meaning of the EU Utilities Directive 2004/17/EC c.q. 2014/25/EU hence private sector procurement procedures will apply. Equipment and works will be purchased through at least two contracts ?one for supply and installation of turbines, others for infrastructure works (Balance of Plant), electrical works etc.

    Projektstatus

    Unterzeichnet - 9/03/2020

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Polen Energie