Date de publication: 8 septembre 2011
Promoteur – Intermédiaire Financier
AS Eesti Energia
Lieu
Description
The project consists of a 220 kt/yr one line waste incineration plant with net energy recovery capacities of 17MW electrical and 50 MW thermal (for district heating).
Objectifs
This will be the first waste incineration plant in Estonia. It will reduce the amount of waste that is currently landfilled. Electricity generated at the facility will be delivered to the grid, and heat to the district heating system.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 50 million
Coût total (montant approximatif)
Approximately EUR 110 million
Aspects environnementaux
The project falls under Annex 1 of the EIA directive, and accordingly an EIA is required. The EIA process (including public participation) has been completed, and the EIA was approved in October 2007 by the Environmental Board, which is the competent authority.
Passation des marchés
The promoter is a public sector controlled entity and thereby required to follow Utilities Directive 2004/17/EC in the procurement.
Statut
Signé - 8/12/2011