    Référence: 20150649
    Date de publication: 20 novembre 2015

    Promoteur – Intermédiaire Financier

    ZWECKVERBAND VERKEHRSVERBUND RHEIN-RUHR

    Lieu

    Description

    Financing of new rolling stock in the densely populated Ruhr region

    Objectifs

    The project consists of the purchase of around 40 electric trains mainly to be used for increased services. The trains will be used on the S-Bahn (suburban trains) Network 2. This network serves amongst others the cities of Dortmund, Duisburg, Essen, Gelsenkirchen and Oberhausen.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 175 million

    Coût total (montant approximatif)

    EUR 350 million

    Aspects environnementaux

    Manufacture of the new train sets will take place in the manufacturer's plant and does not fall within the scope of the Environmental Impact Assessment (EIA) Directive 2011/92/EU; therefore no EIA is required. Compliance with applicable EU directives will be checked as required according to the final scope and procedures for the scrapping/disposal of the old rolling stock, if any.

    Passation des marchés

    The promoter is subject to and follows public procurement rules according to EU regulations. The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2004/18/EC and/or 2004/17/EC as well as Directives 89/665/EEC and 92/13/EEC) as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.
    The contract notice for the supply contract for the trainsets has been published in the Official Journal of the EU (OJEU 2015/S 132-243416). The procurement process followed for these trains, and also for the other project components, will be reviewed during appraisal.

    Statut

    Signé - 13/04/2016

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Allemagne Transports