    The project consists of the development, construction and operation of the 420MW Nachtigal dam and hydroelectric power plant, to be located on the central course of the Sanaga river, 65 km northeast of Yaoundé.

    Objectifs

    The project will provide much-needed economically advantageous renewable electricity supply to the population and businesses of Cameroon.

    Commentaires

    This project represents a coherent development of the hydrological resource of the Sanaga river as a result of the recent construction of the Lom Pangar regulating dam project, whose objective was to help unlock the hydro potential of the Sanaga river, by providing a more stable flow of water during dry periods.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Montant BEI envisagé (montant approximatif)

    EUR 50 million

    Coût total (montant approximatif)

    EUR 1260 million

    Aspects environnementaux

    If located within the EU, the project would fall under Annex I of the Environmental Impact Assessment (EIA) Directive (2011/92/EU) requiring an EIA. An environmental and social impact assessment (ESIA) (2006, 2011) has been produced for the entire project in alignment with national legislation and IFC performance standards, including public consultation. The Bank will assess the environmental and social aspects of the project to ensure that they are acceptable for Bank financing.

    Passation des marchés

    The Bank will assess that procurement of the components to be financed by the Bank has been undertaken in a manner which is acceptable for Bank financing.

    Statut

    Signé - 8/11/2018

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Cameroun Énergie