    Référence: 20140571
    Date de publication: 22 décembre 2014

    Promoteur – Intermédiaire Financier

    Private companies

    Lieu

    Description

    The project concerns investments in (i) the construction and operation of a new glucose and gluten production unit and (ii) an adaptation of the existing bioethanol plant to divert part of its production into Extra Neutral Alcohol (ENA). Both project components are developed on the existing production sites of the promoters' at Zeitz, eastern Germany.

    Objectifs

    Both sub-projects aim at broadening the range of food and industrial products produced by the promoters. The sub-projects will share central facilities with the existing units at the industrial complex. The extension to the existing wastewater treatment plant (WWTP) of the bioethanol plant is required to accommodate increased waste water flows.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 100 million

    Coût total (montant approximatif)

    EUR 208 million

    Aspects environnementaux

    The sub-projects fall under Annex II of Environmental Impact Assessment (EIA) Directive 2011/92/EU. The promoters have submitted project documentation, including a preliminary Environmental Impact Assessment, to the competent authorities. After the corresponding public consultation procedure, authorities have screened the glucose and gluten production plant out. An Environmental Impact Study (EIS) was submitted in early 2014 for the extension project of the bio-ethanol plant. The plant will be built within the existing industrial facilities and will thus only have negligible additional visual impact on the landscape. Because of the project's location any significant negative impact on any site of nature conservation is considered unlikely to occur. There are no Natura 2000 sites in the surroundings of the plant.

    Passation des marchés

    The two promoters are private companies of industrial or commercial character, not operating in the utilities sector as their main economic purpose, and are therefore not subject to EU directives on procurement. They apply well-established procurement procedures that are in line with the standard practice for this industry, in the best interests of the project and therefore in line with the Bank’s procurement policy for private industry projects.

    Statut

    Signé - 17/12/2014

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Allemagne Industrie