Date de publication: 10 décembre 2014
Promoteur – Intermédiaire Financier
The borrower is the People's Republic of China, represented by the Ministry of Finance, who will on-lend to a privately owned project company.Lieu
Description
The project is an allocation under the China Climate Change Framework Loan II, and consists of the financing of a biomass CHP unit (25 MWe – 45 MWth) in the city of Gushi (Henan province, China). The plant will run on biomass sourced regionally (crop stalks). The electricity will be fed into the national grid and the generated heat will be supplied to a heat/steam network currently under development.
Objectifs
The project will generate heat and electricity from locally sourced, sustainable agricultural biomass residue, replacing inefficient and polluting coal-fired boilers in an urban environment (when the project is completed, existing small and inefficient coal steam boilers will be decommissioned), with a mainly positive environmental and social impact.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 30 million
Coût total (montant approximatif)
EUR 64 million
Aspects environnementaux
The project will have a positive impact on the environment by reducing the need for fossil fuels for energy and heating and thus indirectly reducing pollution (mainly airborne pollution including CO2) in an urban environment. An environmental impact assessment (EIA) has been performed for the project. The Bank will review the EIA process and documentation during appraisal and ensure adherence to its environmental and social standards.
Passation des marchés
The Bank will require that the implementation of the project will be done in accordance with the Bank's Guide to Procurement. The Bank will monitor the procurement process to ensure compliance with our Guide.
Statut
Approuvé - 21/10/2015
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).