Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
    Référence: 20120673
    Date de publication: 24 juillet 2013

    Promoteur – Intermédiaire Financier

    MINISTRY OF TRANSPORT

    Lieu

    Description

    Construction of 5 sections of the S8 expressway from Warsaw to Bialystok

    Objectifs

    The project is located in a Convergence region and is therefore eligible under Article 309(a). The project road is included in the current TEN-T and is proposed for inclusion in the TEN-T comprehensive (i.e. non-core) road network as part of the on-going Revision Guidelines to be approved by the Council and Parliament. The project is therefore also eligible under Article 309 (c) of the EC treaty. The project is expected to benefit from grant finance under the Operational Program Infrastructure and Environment in the next financing perspective. The consistency of the project with the policy for lending to the transport sector (Decision CA/452/11) depends on its economic profitability and will be confirmed during appraisal.

    Commentaires

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    PLN 680 million (EUR 163 million)

    Coût total (montant approximatif)

    PLN 1706 million (EUR 408 million)

    Aspects environnementaux

    The project falls under Annex 1 of the Environmental Impact Assessment Directive 2011/92/EU and is the subject to a full EIA procedure. The provisions of the Habitats Directive (92/43/EEC) and Birds Directive (2009/147/EC) apply. None of the sections appear to cross the Natura 2000 areas but are close to the following protected zones Bagienna Dolina Narwi (PLB 200001) and Bagno Wizna (PLB 200005). During appraisal the impact of the project on the environment will be determined.

    Passation des marchés

    The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2004/18/EC and 2007/66/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.

    Statut

    Signé - 17/12/2013

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Pologne Transports