    This project comprises the construction of high voltage transmission infrastructure required to evacuate electricity from newly-constructed hydropower plants in the Trishuli River basin into the national grid, as well as a rural electrification component to supply power to communities in the vicinity of the project areas. The project also includes an upgrade of the national Load Dispatch Centre (LDC).

    Objectifs

    The project will deliver new supplies of hydroelectricity to meet increasing demand in Kathmandu and the rest of Nepal. As such, it will address the shortage of power in the Nepalese grid as well as the efficient integration of new generation capacity from renewable sources (hydropower).

    Commentaires

    This operation is covered by the EU Guarantee for EIB loans outside the EU.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 30 million

    Coût total (montant approximatif)

    EUR 65 million

    Aspects environnementaux

    The promoter has conducted initial environmental examinations that indicate that the impacts of the main project components are moderate, within acceptable limits and can generally be mitigated. The majority of the land required for the transmission line will be available for cultivation after completion. A limited number of households will be affected, and no existing residences will require relocation. Detailed environmental & social management and land acquisition & compensation plans will be prepared prior to the start of any construction activities. The Bank will ensure that appropriate measures are taken to protect the environment and the rights of people affected by the project, and to avoid, reduce, mitigate and compensate for the impacts.

    Passation des marchés

    The Bank will require the promoter to ensure that implementation of the project is carried out in accordance with the Bank's Guide to Procurement as applicable to operations in the public sector.

    Statut

    Signé - 3/12/2015

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Népal Énergie