Date de publication: 6 août 2012
Promoteur – Intermédiaire Financier
SLOVENSKE ELEKTRARNE ASLieu
Description
9-year investment programme mainly in renewable power generation focusing on overhauling/refurbishment and capacity expansion of the promoter's hydro power plant portfolio.
Objectifs
The project concerns an investment programme, comprising approximately 100 schemes, which relate primarily to the overhaul/refurbishment of existing hydro power stations as well as capacity expansion with new small run of river hydro units - up to around 3.5MW in capacity. The project schemes will be dispersed throughout the Slovak Republic.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 60 million
Coût total (montant approximatif)
EUR 120 million
Aspects environnementaux
Considering their technical characteristics, the programme schemes fall under Annex II of the EIA Directive (2011/92/EU), and consequently it is the responsibility of the competent authority to determine the need for an Environmental Impact Assessment (EIA). Given the nature of the project schemes (overhaul/refurbishment of existing hydro, small run of river construction) it is expected that the vast majority of the schemes will not require an EIA.
Passation des marchés
The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 2004/17/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.
Statut
Signé - 2/09/2013
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).