Recherche Fr menu Portail client du Groupe BEI
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
Référence: 20120111
Date de publication: 21 mai 2012

Promoteur – Intermédiaire Financier

ACEA S.p.A.

Lieu

Description

Investments to reinforce and extend the electricity distribution network in the Rome metropolitan area

Objectifs

The project will enable the promoter to cater for demand/peak demand growth in specific areas of the network, to reduce losses, and to improve the quality and the reliability of electricity supply.

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 100 million

Coût total (montant approximatif)

EUR 255 million

Aspects environnementaux

Current information suggests that the project components could fall under Annex II of the Environmental Impact Assessment Directive (85/337/EEC as amended in 1997 and 2003), requiring the competent authority to determine the need for an EIA in line with the Directive. This will be further assessed during appraisal.

Passation des marchés

The promoter tenders works, supplies and services contracts following procurement rules of relevant national and EU legislation, as defined by Directive 2004/17/EC, including publication in the Official Journal of the EU where appropriate.

Statut

Signé - 25/10/2012

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Italie Énergie