    Référence: 20120052
    Date de publication: 2 mai 2012

    Promoteur – Intermédiaire Financier

    BUNDESREPUBLIK DEUTSCHLAND

    Lieu

    Description

    The project concerns the widening of a 65km section of the A7 motorway between Hamburg and Neumünster to six / eight lanes. The 30-year concession will also include the operation and maintenance of most of the widened motorway section and will be remunerated on an availability basis.

    Objectifs

    The motorway A7, part of the trans-European transport network (TEN-T), is the longest motorway in Germany and one of most important North-South links between Scandinavia and central Europe. The project helps adapt the motorway to increasing traffic and maintain it as an efficient and attractive transport link.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 250 million

    Coût total (montant approximatif)

    EUR 657 million

    Aspects environnementaux

    The project consists in the upgrading on an existing 2x2-lane motorway therefore it falls under Annex II of the EIA Directive 85/337/EEC amended (codified by Directive 2011/92/EU of 13 December 2011), and hence the competent authority decides on the requirement for a full EIA. Compliance with the EIA Directive, the Habitats Directive (92/43/EEC) and Birds Directives (79/409/EEC) and NATURA 2000 will be verified in detail during appraisal. The project was included in national strategic planning before the application of SEA Directive.

    Passation des marchés

    The tender process was launched in December 2011 with prior publication of the contract notice (2011/S 241-391050) under the heading “negotiated procedure”. The concession will include design, construction, financing, maintenance and operation.
    Procurement procedures and compliance with Directive 2004/18/EC will be verified in detail during appraisal.

    Statut

    Signé - 26/08/2014

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Allemagne Transports