    Référence: 20100177
    Date de publication: 29 septembre 2010

    Promoteur – Intermédiaire Financier

    CEZ a.s.

    Lieu

    Description

    Investment programme comprising a series of similar land-based, multi-megawatt photovoltaic power plants located in the Czech Republic.

    Objectifs

    The development of renewable energy capacity, using indigenous sources of energy, will support national and European targets for renewable energy generation and contribute to environmental and security of energy supply objectives. Electricity generation from PV sources will displace fossil fuel-fired generation and the associated emissions of CO2, NOX and SO2. Additionally, the investments included in this operation are situated in Convergence Regions (“Strictu Sensu” and “Phasing-In”).

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 200 million.

    Coût total (montant approximatif)

    Estimated at EUR 400 million.

    Aspects environnementaux

    The environmental and social impacts of the land-based solar PV installations are likely to be limited to visual effects. Based on current information, all projects under the investment programme fall under Annex II of the Environmental Impact Assessment directive (85/337/EEC as amended by 97/11/EC and 2003/35/EC), leaving it to the competent authority to decide on the need for an EIA in line with the Directive. The project shall comply with national and EU environmental legislation.

    Passation des marchés

    The promoter is a public undertaking in the sense of the Utilities Directive 2004/17/EU and would thus have to apply public procurement procedures accordingly. However, some of the schemes have been fully or partly developed by private entities and corresponding supply/works contracts may have been awarded prior to the project acquisition by the promoter. In these cases, publication of contract notices was not required. The Bank will ensure that suitable procurement procedures will be applied by the promoter and/or the borrowers.

    Statut

    Signé - 18/11/2010

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    République tchèque Énergie