    Référence: 20090712
    Date de publication: 22 août 2012

    Promoteur – Intermédiaire Financier

    WEST AFRICAN POWER POOL

    Lieu

    Description

    The power interconnection between Côte d'Ivoire, Liberia, Sierra Leone and Guinée (CLSG) is a priority project of the West African Power Pool (WAPP) that will enable power exchanges between the four countries.

    Objectifs

    This project will enable power exchanges between Côte d'Ivoire, Liberia, Sierra Leone and Guinée, thereby improving the supply of electricity in these post-conflict countries. In the medium term, the project should enable the development of the hydropower potential of Guinée. In Sierra Leone, the availability of low cost and reliable electricity is a necessary prerequisite for the recovery of economic and human development activites.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 75 million

    Coût total (montant approximatif)

    EUR 370 million

    Aspects environnementaux

    The project, if implemented inside the EU, would fall under Annex 1 of EIA directive, requiring an EIA. The promoter has conducted an ESIA with an international consultant. The process has included public consultation. The identified environmental risks are typical for high voltage transmission projects, including vegetation and forest cleaning, visual impact, avifauna collisions and resettlement of people from transmission corridor. The study includes appropriate mitigating measures like re-routing the line at the areas of environmental hotspots, visual impact minimisation and resettlement action plan.

    Passation des marchés

    The Bank will require that the procurement is carried out in accordance with the EIB's Guide to Procurement and will provide guidance to the promoter.

    Statut

    Signé - 10/12/2012

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Régional - Afrique de l'Ouest Énergie