    Référence: 20090551
    Date de publication: 8 avril 2011

    Promoteur – Intermédiaire Financier

    Polskie LNG SA

    Lieu

    Description

    The project consists of the construction and operation of a new Liquefied Natural Gas import terminal on the Polish Baltic Sea coast at Swinoujscie. The terminal will have a throughput capacity of 5 Gm3/a.

    Objectifs

    The project will diversify import capacity of natural gas in line with national energy policy as established by Poland and will contribute to the development of the energy network supplying the European Union.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Up to EUR 150 million

    Coût total (montant approximatif)

    Approx. EUR 926 million

    Aspects environnementaux

    The LNG terminal was required by the Polish competent authority to undergo an environmental impact assessment because of its technical characteristics, its location in environmentally protected Natura 2000 areas and because of its direct relation with new jetty, breakwater and pipeline developments, likewise located in protected areas. The EIA was submitted to Polish authorities at the end of 2008. After passing through a public consultation process, during which no major objections have been received, the competent authority approved the EIA in 2009. The study’s overall conclusion is that the terminal will not have significant negative impacts on sites of nature conservation importance, and that the investment will not threaten the integrity of the protected zones.

    Passation des marchés

    The procurement process was launched in mid 2009 by an announcement at national level and in the international press, inviting interested companies to pre-qualify for project services and for the EPC contract. It concluded in main contracts being awarded in 2010.

    Statut

    Signé - 14/12/2011

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Pologne Énergie