Date de publication: 6 août 2009
Promoteur – Intermédiaire Financier
Private/Disitribution System Operator in PolandLieu
Description
The project comprises a large number schemes for extending and modernising the promoter’s electricity networks covering the investment period 2009-2011.
Objectifs
The project includes the construction and refurbishment of 1,300 km of MV lines, 3,100 km of LV lines and around 2,600 MV/LV substations as well as few HV lines for the connection of renewable energy sources, mainly wind farms.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 200 million.
Coût total (montant approximatif)
EUR 572 million.
Aspects environnementaux
All the projects schemes will fall under Annex II of the EIA directive, leaving it to the national competent authority to decide whether an EIA will be required in line with screening criteria specified in the directive. The criteria applied by the national competent authorities in Poland will be investigated during the appraisal. In line with the Bank guidelines the evaluation will assess the promoter’s capacity to address environmental and biodiversity issues in an appropriate way.
Passation des marchés
The promoter follows public procurement procedures in compliance with the Directive 2004/17/EC and with the Polish Public Procurement Act. The promoter’s approach for the procurement of works, goods and services will be further evaluated during the appraisal.
Statut
Signé - 16/12/2009
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).