    Référence: 20080679
    Date de publication: 9 juin 2009

    Promoteur – Intermédiaire Financier

    Stora Enso Oyj

    Lieu

    Description

    The project comprises two parts. Part I concerns investments in research, development and innovation related to pulp, paper packaging and forest products. Part II includes design, construction and operation of a combined heat and power generation facility in Ostroleka, Poland.

    Objectifs

    The RDI part of the project will support the research activities and technical development within a European paper and forest products manufacturer. The power plant project is located in a convergence region and the project will employ an efficient, combined heat and power technology and help to increase the energy self-suffiency of the promoter.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Up to EUR 230 million.

    Coût total (montant approximatif)

    The RDI related project cost is estimated at up to EUR 348 million. in total. The project cost related to the power plant to be is estimated at EUR 137 million. This leads to total project costs of EUR 485 million.

    Aspects environnementaux

    For the RDI part, an EIA will not be necessary according to EIA Directive as long as existing RDI facilities are used. The power plant is part of a bigger investment programme which falls under Annex I of Directive 85/337/EEC and is subject to an EIA. This part will require appropriate environmental permits under IPPC Directive 2008/1/EC. Full environmental details will be assessed during appraisal, including possible impacts on protected flora and fauna.

    Passation des marchés

    The promoter is a private company, not operating in the utilities sector, and is not covered by EU directives on procurement. During the appraisal, the Bank will verify the promoter’s procurement procedures to ensure that the project benefits from market-based competition between potential subcontractors.

    Statut

    Signé - 9/02/2010

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Finlande Pologne Suède Énergie Industrie