    Référence: 20080329
    Date de publication: 16 octobre 2008

    Promoteur – Intermédiaire Financier

    Ministry of Finance.

    Lieu

    Description

    This project is a proposed loan allocation under the China Climate Change Framework Loan(CCCFL). Four subprojects are considered:

    1-Xinyang windfarm project, Henan province: The proposed subproject is composed of four different windparks for a total of 124 turbines with a total installed capacity of 105.5 MW.

    2-Dongfang windfarm project, Hainan province: The subproject is located in one site along the shoreline in the Dongfang municipality for a total installed capacity of 49.5 MW.

    3-DengLouJiao windfarm project, Xuwen county, Guangdong province: The subproject is located in one site along the shoreline of the Jiaowei city for a total installed capacity of 49.5 MW.

    4-Yongshi windfarm project, Xuwen county, Guangdong province: The subproject is located in one agricultural area on the most southern limits of the Zhangjiang municipality for a total installed capacity of 49.5 MW.

    Objectifs

    The project supports EU and Bank policy objectives with regard to combating climate change and promoting renewable energy generation. The operation is eligible under the Asia and Latin America (ALA) mandate in line with the core objectives of contributing to environmental sustainability.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Up to EUR 140 million.

    Coût total (montant approximatif)

    EUR 253 million.

    Aspects environnementaux

    The key objective of these allocations is to contribute to climate change mitigation. If located in the EU, the sub-projects would fall under Annex II of the Environmental Impact Assessment (EIA) Directive, which would leave it to the competent environmental authorities to determine the requirement for EIAs based on the screening criteria specified in Annex III of the same directive. The Chinese EIA law and regulations require EIAs to be prepared for all the sub-projects.

    The investment schemes shall be prepared in line with the relevant national and EU environmental standards, including due consideration for protection of sites of nature conservation, as well as the social safeguards of the Bank. These issues will be addressed during the appraisal of the subprojects.

    Passation des marchés

    Procurement will be undertaken in accordance with the Bank’s Procurement Guidelines.

    Statut

    À l'examen - 16/10/2008

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Chine Énergie