Date de publication: 9 juillet 2008
Promoteur – Intermédiaire Financier
Orkuveita Reykjavikur (Reykjavik Energy)Lieu
Description
The project concerns the expansion of the Hellisheiði geothermal power plant by additional 90 MWel and the construction of a new 90 MWel geothermal power plant at Hverahlíð.
Objectifs
The objective of the new power units is to meet increasing demand for electricity in the industrial, residential and commercial sectors.
Secteur(s)
Montant BEI envisagé (montant approximatif)
Up to EUR 170 million.
Coût total (montant approximatif)
Approximately EUR 340 million.
Aspects environnementaux
Both investment projects, i.e. stage 5 of the Hellisheiði Plant and Hverahlíð Plant have been subject to a full Environmental Impact Assessment (EIA) procedure in accordance with national legislation (Icelandic EIA Act no. 106/2000), which is based on the EU Directive 85/337 with its amendments.
Passation des marchés
The procedures employed for awarding works, supplies and services contracts for the various components of the project are in accordance with Icelandic legislation, which is based on the relevant EU Directive (2004/17/EC) and includes the requirement to publish tender announcements in the EC Official Journal.
Statut
Signé - 20/11/2009
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).