Date de publication: 9 juin 2005
Promoteur – Intermédiaire Financier
Glas Cymru Cyfyngedig.Lieu
Description
The project comprises the first phase of Welsh Water’s capital programme for the 2005-2010 period, which is approved and monitored by the industry regulator OFWAT. The project consists of a large number of water supply and wastewater schemes located throughout Wales.
Objectifs
The proposed programme aims at supporting sustainable environmental and customer service standards set by EU and national legislation as well as regional development. The project will therefore contribute to improving the quality of life of the population in the Wales.
Secteur(s)
Montant BEI envisagé (montant approximatif)
GBP 100 million.
Coût total (montant approximatif)
Estimated to be some GBP 516 million.
Aspects environnementaux
The schemes included in the project fall under Annex II of Directive 97/11/EC. Environmental Impact Assessment (EIA) procedures are carried out where required by the competent authorities and mitigating measures are applied as appropriate.
Passation des marchés
The project falls under the EU Procurement Directive (Dir 2004/18 or 2004/17/EEC) coordinating the procurement procedures of entities operating in the water, energy, transport and telecommunications sectors. The borrower has confirmed that it complies fully with its requirements in reference to the Procurement Directive and its amendment.
Statut
Signé - 5/12/2005
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).