    Référence: 20050007
    Date de publication: 7 novembre 2005

    Promoteur – Intermédiaire Financier

    Hamburger Hafen-und Logistik- Aktiengesellschaft (HHLA).HHLA and HHLA Container Terminal Buchardkai GmbH (CTB) a 100% HHLA subsidiary.

    Lieu

    Description

    The port of Hamburg is the second largest port for container traffic in Europe. Existing container terminals are close to saturation. The project consists in the expansion of the container terminal Buchardkai (CTB), currently the biggest container terminal in the port of Hamburg, whose capacity has been reached. The Project proposed for EIB financing is the infrastructure and equipment to be implemented by HHLA within this first phase to 2010.

    Objectifs

    Through a comprehensive rearrangement of container handling logistics on Burchardkai, the present project will improve the efficiency and increase the capacity of container handling in the port of Hamburg. Economic benefits comprise the economic surplus associated with the handling of additional container volumes, as well as reductions in throughput times and handling cost.

    The investment hence is eligible under Article 267 of the EU Treaty, point c (transport infrastructure of common interest).

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 147 million

    Coût total (montant approximatif)

    EUR 295 million

    Aspects environnementaux

    The project is situated in an existing container terminal that will not be expanded in physical size, but with new quays and a much denser storage of containers, will, in phases to 2014, double its capacity. The project forms part of the overall Port Master Plan 2005-2010, which was developed before July 2004 applicable date for an assessment under the SEA Directive. The project falls under Annex II of the EIA Directive and an EIA has been carried out by the Hamburg Port Authority for the quay and berth works and in certain aspects, such as noise, for the overall terminal expansion. Final environmental approval for the EIA is expected in early 2006.

    Passation des marchés

    Tendering for works and equipment supply contracts for Project components has been, or will be, made in line with EU Directives on procurement, including publication in the OJEU.

    Statut

    Signé - 22/12/2005

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Allemagne Transports