The project consists of the construction of 60 km of motorway between the cities of Cernavoda (150 km west of Bucharest) and the Black Sea port of Constanta as well as of the by-pass of Constanta.
Objectifs
The proposed section will provide an important link between Bucharest and the Black Sea port of Constanta and will create benefits in vehicle operating costs, time savings and improved safety for road users while reducing adverse environmental impacts along the existing roads, particularly inside towns.
Secteur(s)
Montant BEI envisagé (montant approximatif)
Up to EUR 187.5 million.
Coût total (montant approximatif)
EUR 250 million.
Aspects environnementaux
The project would fall within Annex I of the directive 97/11/EC on environmental impact assessment if the project were in a Member State and therefore an environmental impact assessment (EIA) would be required. This EIA, including public consultations, is currently under preparation.
Passation des marchés
All the construction works and design and supervision contracts above the thresholds in the EU procurement directives will be tendered internationally with prior publication in the OJEU and in accordance with the EIB Guide to Procurement. The Promoter is familiar with the EIB requirements for the tendering procedures.
Statut
Signé - 27/12/2005
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).